Three coordinated terrain-following earthworks missions covering five kilometres of corridor, organized from the furthest section back toward the project access route.
All missions use Smart Oblique, approximately 2.02 cm/pixel GSD, 75 m AGL, 80% forward / 80% side overlap, Direct Ascent and real-time terrain following. Multiple batteries may be used with breakpoint resume.
TOP near KM 33+000 · 1.039 km corridor · 7.36 km planned route · 20 min 41 sec · 1,331 images · 10.6 m/s · 70 m left / right extension · Direct Ascent to 60 m · terrain follow enabled · RTH.
TOP near KM 30+000 · 2.068 km corridor · 14.5 km planned route · 34 min 57 sec · 2,613 images · 10.6 m/s · 80 m left / right extension · Direct Ascent to 40 m · terrain follow enabled · RTH.
TOP near KM 27+000 · 2.002 km corridor · 14.1 km planned route · 33 min 14 sec · 2,517 images · 10.5 m/s · 60 m left / right extension · Direct Ascent to 50 m · terrain follow enabled · RTH.
At each TOP, register the ground ASL before launch. Capture a panorama at 50 m above the TOP and register the aircraft ASL at 50 m.
| Mission | Coverage | TOP | Planned route | Duration |
|---|---|---|---|---|
| Mission 1 | 32+000-33+000 | 33+000 | 7.36 km | 20 min 41 sec |
| Mission 2 | 28+000-30+000 | 30+000 | 14.5 km | 34 min 57 sec |
| Mission 3 | 25+000-27+000 | 27+000 | 14.1 km | 33 min 14 sec |