Operational structure documentation plan.
Connect to Red CORS → obtain FIX → establish the point in Survey → photograph the point → stop Red CORS.
Set the GNSS base on the Survey point → start Local NTRIP → start logging. On the controller, confirm Local NTRIP—or Red CORS when documenting structures.
After mission teardown, stop logging and transfer the log file to the tablet desktop.
Record the TOP during setup. At each structure, record panorama AGL and aircraft ASL before the panorama, top-down and perspective photographs. Separate new missions/ TOPs with four asterisks.
KM26+700 TOP ASL 2611 Pano 50 m · ASL 2661
KM96+643 PSV 69 Pano 80 m AGL · ASL 2691 Foto cenital, fotos KM96+704 ODT Pano 58 m AGL · ASL 2669 Foto cenital, fotos, maquinaria
**** Misión fotogrametría KM97+300 TOP Pano 50 m · ASL 2614 KM93+490–KM97+220
Repeat the August 6 corridor with a 100 m extension to KM41+600 for a six-week progress comparison. Document the four structures separately, in the listed order. Register TOP, TOP ASL and TOP +50 m panorama ASL before capture.
Use Copy to retain the chainage-first delivery identifier exactly as shown.
| # | Structure | Required capture | Sequence |
|---|---|---|---|
| 01 | KM40+045 ODT | Panorama + AGL/ASL + top-down + perspectives | 260917 · 01 |
| 02 | KM40+050 PSV | Panorama + AGL/ASL + top-down + perspectives | 260917 · 02 |
| 03 | KM40+245 ODT | Panorama + AGL/ASL + top-down + perspectives | 260917 · 03 |
| 04 | KM40+600 ODT | Panorama + AGL/ASL + top-down + perspectives | 260917 · 04 |
Document the ODTs in the listed order, subject to site access. The locations span approximately 1.79 km of chainage. The supplied photogrammetry mission covers KM46+500–KM49+000; document the structures separately.
Use Copy to retain the chainage-first delivery identifier exactly as shown.
| # | Structure | Required capture | Sequence |
|---|---|---|---|
| 01 | KM46+806 ODT | Panorama + AGL/ASL + top-down + perspectives One Ø1.50 m pipe | 260918 · 01 |
| 02 | KM46+918 ODT | Panorama + AGL/ASL + top-down + perspectives One provisional stop · adjustment reference KM46+921 | 260918 · 02 |
| 03 | KM47+146 ODT | Panorama + AGL/ASL + top-down + perspectives Two Ø3.05 m pipes · document both barrels | 260918 · 03 |
| 04 | KM47+771 ODT | Panorama + AGL/ASL + top-down + perspectives Two Ø2.44 m pipes · document both barrels | 260918 · 04 |
| 05 | KM48+317 ODT | Panorama + AGL/ASL + top-down + perspectives One Ø1.50 m pipe | 260918 · 05 |
| 06 | KM48+420 ODT | Panorama + AGL/ASL + top-down + perspectives One Ø1.50 m pipe | 260918 · 06 |
| 07 | KM48+593 ODT | Panorama + AGL/ASL + top-down + perspectives One Ø1.50 m pipe | 260918 · 07 |