33Visual · Aerial Intelligence

KM93+490 – KM97+220

Real-time terrain-following corridor mapping and perspective and top-down documentation of eighteen ODT, PIV and PSV structures across the August 26–28 field program.

260826–260828 · August 26–28, 2026
KM93+490 – KM97+220 · Corridor mission and structure schedule
The FlightHub corridor and TOP follow the supplied KMZ. Map filters separate the ATAT structure schedule by day; the two structures absent from the latest itinerary remain visible as pending schedule.
Map legendStructure schedule
KM93+490 – KM97+220 · corridor mapping.
August 26 · six structures.
August 27 · five structures.
August 28 · five corridor structures.
Pending schedule · two structures.
FlightHub TOP · RS2+, Starlink and RC setup.
Select a marker · Ctrl / Command + scroll to zoom

Flight plan

The programmed FlightHub strip uses a 2,000 m cutting distance, producing manageable field sections while keeping one continuous corridor geometry and a common RTK setup.

KM93+490 – KM97+220Cenital · terrain follow

3.73 km corridor · 75 m AGL · 70 m left/right extensions · 80% / 80% overlap · 21 m/s global flight speed · elevation optimization and real-time terrain follow enabled · timed-interval photography.

FlightHub TOP · near KM94+656: supplied takeoff reference for the RS2+, Starlink and RC setup. Confirm approved access, open sky, VLOS, command link and the complete ascent, transfer and RTH profile before execution.

Eastern field check: verify visibility and command link through the terrain-sensitive KM96+300–KM97+220 section.
3.73 kmCorridor
18Structures
16Scheduled
2Pending schedule
CoverageModeOperational scope
KM93+490 – KM97+22075 m AGL · NadirCorridor mapping · 2,000 m cutting distance
KM93+540 – KM97+109Structure capture18 total · 16 scheduled · 2 awaiting assignment
KM96+100 PIV s/n and KM96+620 ODT do not appear in the latest ATAT itinerary. They remain in the complete structure list as pending schedule.

Field schedule

Wednesday · August 26Six structures

Office ETA 08:45 · ETD 09:00 · first target KM93+540 ODT at 09:40 · ETC KM95+550 ODT at 16:40 · RTB 17:20.

Thursday · August 27Five structures

Office ETA 08:45 · ETD 09:00 · first target KM95+787 ODT at 09:30 · ETC KM96+460 ODT at 16:00 · RTB 16:30.

Friday · August 28Five + Banco

Office ETA 08:45 · ETD 09:00 · first target KM96+639 PSV 69 at 09:30 · ETC Banco Santo Domingo KM99+160 at 17:00 · RTB 17:30.

Structure capture

Capture every listed structure with perspective and top-down photographs. Use the copy control beside the name to copy the delivery-ready identifier exactly as shown.

#StructureCapture scopeSchedule
01
KM93+540 ODT
Perspective + top-downAug 26 · 01
02
KM93+836 ODT
Perspective + top-downAug 26 · 02
03
KM94+637 PIV 80
Perspective + top-downAug 26 · 03
04
KM95+152 ODT
Perspective + top-downAug 26 · 04
05
KM95+345 ODT
Perspective + top-downAug 26 · 05
06
KM95+550 ODT
Perspective + top-downAug 26 · 06
07
KM95+787 ODT
Perspective + top-downAug 27 · 01
08
KM95+834 ODT
Perspective + top-downAug 27 · 02
09
KM95+915 ODT
Perspective + top-downAug 27 · 03
10
KM96+100 PIV s/n
Perspective + top-downPending schedule
11
KM96+340 ODT
Perspective + top-downAug 27 · 04
12
KM96+460 ODT
Perspective + top-downAug 27 · 05
13
KM96+620 ODT
Perspective + top-downPending schedule
14
KM96+639 PSV 69
Perspective + top-downAug 28 · 01
15
KM96+704 ODT
Perspective + top-downAug 28 · 02
16
KM96+812 ODT
Perspective + top-downAug 28 · 03
17
KM97+001 ODT
Perspective + top-downAug 28 · 04
18
KM97+109 ODT
Perspective + top-downAug 28 · 05
Candidate corridor extension

KM97 – KM99

Under evaluation

Proposed 1.89 km orthomosaic extension with seven ODTs in range, plus KM99+105 PSV immediately beyond the corridor endpoint. The ortho mission uses one setup near KM97+100; each structure is approached separately by vehicle to keep the pilot, RC, Starlink and local NTRIP source close to the aircraft.

Map legendProposed operating scope
KM97+000 – KM99+000 · orthomosaic corridor.
ODT already included in the Friday structure list.
Additional ODT within the proposed extension.
KM99+105 PSV · 105 m beyond the corridor endpoint.
Proposed ortho TOP near KM97+100.
Select a marker · Ctrl / Command + scroll to zoom

Operational plan

1.89 kmDraft route
8Structure targets
75 mAGL terrain follow

Ortho mission: keep the Reach RS2+, Starlink and RC together at the KM97+100 TOP for one stable local NTRIP base and one continuous RINEX observation.

Structure capture: treat each ODT and PSV as a separate drive-up operation. Reposition the field team close to the target to preserve VLOS, command link and NTRIP connectivity.

70 m + 70 mLeft / right corridor extension
80% / 80%Side / forward overlap
Real-timeTerrain follow enabled
20:36 · 1,158Current draft time · images
Base movement: do not move the RS2+ during the corridor mission. If it is moved for a separate structure flight, start a new logged base setup and confirm the new base position before takeoff.

Structures under the proposed corridor

#StructureMission statusField approach
01
KM97+001 ODT
Friday listDrive-up structure capture
02
KM97+109 ODT
Friday listDrive-up structure capture
03
KM97+741 ODT
Added coverageDrive-up structure capture
04
KM98+059 ODT
Added coverageDrive-up structure capture
05
KM98+331 ODT
Added coverageDrive-up structure capture
06
KM98+499 ODT
Added coverageDrive-up structure capture
07
KM98+715 ODT
Added coverageDrive-up structure capture
08
KM99+105 PSV
Beyond corridorDrive-up structure capture
KM99+105 PSV is included as a structure target but remains outside the KM97+000–KM99+000 orthomosaic corridor. Map positions are planning references; validate the exact structure access point in the field.