Interactive mission-planning layer for Viaducto Cahuacan III, planned as a dedicated KM 39 linear mapping block with 2 cm/pixel GSD, smart oblique capture, and 80% / 80% overlap.
This map is intended as a field-planning reference for Viaducto Cahuacan III within the AT-AT construction highway project. It combines the project-plan stationing, the FlightHub KMZ route, the viaduct span, essential ODT / utility references, and the primary takeoff / landing candidate.
| Reference | Station / Value | Use |
|---|---|---|
| Viaducto Cahuacan III | KM 38+995.744 to KM 39+455.748 | Primary structure documentation span |
| FlightHub linear route | 715 m | Active mapping strip length |
| Mission distance / duration | 6,377.5 m · approx. 13 min | Total flight path and operational estimate |
| Primary takeoff / landing candidate | 19.605249, -99.437879 | KMZ takeoff reference, field verification required |
| ASL flight block | 2,934.5 m ASL | Mission altitude for Cahuacan III documentation |
| Terrain surface reference | 2,860 m ASL | FlightHub terrain reference for this mission block |
| Capture settings | 2 cm/pixel · 80% / 80% · Smart Oblique | GSD, overlap and capture profile |
| ODT / Context | Station | Status |
|---|---|---|
| OI LAP 2 1/2", 3/4" Ø | KM 38+814.62 | Essential utility / ODT context west of the active span |
| Canal de riego 24" · estructura metálica | KM 38+574.79 | Essential drainage / irrigation context west of the active block |
| PIV 29 A | KM 38+527.430 | Essential road-structure context west of Cahuacan III |